Track Record 2025
2025 was dominated by one very large build — the corporate project that 24.09 promised updates on. Here is how it landed. We are back-filling the rest of this page from the job diaries — more entries coming.
August 1
25.03 · Corporate cafe build-out — completed, doors open
commenced September 2024 as 24.09 · steel framing, ground works, full commercial kitchen infrastructure, extensive shop millwork · about 10% over budget, about 30 days behind schedule — mostly communication challenges between the mall owner and the City, negotiated as best we could · full story in the Journal
Year end
25.01 · Large commercial office and clinic — commences
delayed start due to City permitting process · once construction commenced, we were on time — a 6-month commercial build · completed June 2026, about 10% over budget