Our record continues: on time, on budget — or we say so plainly. 2026 so far: a steady run of fast small jobs, three completions in a single June, and our flagship whole-main-floor renewal closed on time against a very tight schedule.
January 15
25.05 · Display cabinetry with glass doors, private residence
install needed a follow-up visit to tweak to standard — old home with out-of-plumb walls; we reworked it until it was right · on budget, as quoted · invested in new precision site equipment as a direct result
January 30
26.03 · Apartment building — replace damaged cabinets and ceiling hatch due to accident on site
on time · on budget
February 15
26.06 · Designer client — sculptural coffee-table base
on time · on budget · built in our shop, adjusted, redelivered — the designer channel keeps bringing us back
March 15
26.08 · Private client condo — refresh: paint, plumbing, finishing
final bathroom counter install delayed due to product shipment from Montreal · on budget · client pleased with final result
March 30
26.13 · Flagship whole-main-floor renewal — commences
our largest project of the year · extensive custom millwork from our shop
April 15
26.17 · Private client — outdoor living + gas line project
design-to-build in nine weeks
June 20
26.17 · Outdoor living + gas line — completed
on budget · some delays due to incessant, record-breaking rain · one change order (gas line), client-requested, pre-quoted
June 21
26.20 · Private client — same-week service repair
called, quoted, fixed — inside a month
July 15
26.23 · Downtown condo refresh
on time · on budget
July 30
26.29 · Luxury highrise residence — interior renewal signed
porcelain-slab fireplaces, premium counters, motorized shades · underway now — completion targeted for December
August 1
26.13 · Flagship whole-main-floor renewal — completed
closed on time, against a very tight schedule · extensive custom millwork throughout — watch the Journal for the full story
August — in progress
26.28 · kitchen design/build · 26.22 · apartment renewal — committed, starting · 26.30 · insurance-restoration basement